Edwards Lifesciences – LFS#2

Types of Systems Commissioned
• HVAC and Controls
• Plug Load Controls
• Lighting and Daylighting Controls
• Plumbing Systems
• Landscape & Irrigation System


Building Area
106,360 SF

Date of Completion
May 2016

Type of Commissioning
LEED Cx and CALGreen Cx


DSC05318 Office Layout
IMG_1171


Project Overview

BTU Engineers is serving as the Commissioning Authority (CA) for Edwards Lifesciences LFS #2 building, providing LEED Fundamental and Enhanced Cx and CALGreen Commissioning.

Edwards Lifesciences is constructing a new office building to be located in 1411 McGaw Avenue Irvine, CA. This is a 4-story office building with a café located on the 1st floor. Total building area excluding the cafe is 83,732 SF and cafe area is 22,628 SF.