Caltrans District 4


Annual Energy Savings
1,240 MMBTU


Annual Cost Savings
$55,996

Simple Pay Back
6.9 years


Building Area
525,500 SF


Date of Completion
March 2018


Project Overview

BTU Engineers worked on Caltrans District 4 Office Building located in Oakland, CA. Total conditioned space is 525,000 sq.ft. for this facility. We provided LEED-EBOM services for this building. This building earned a LEED Gold status under v4. BTU Engineers performed ASHRAE 62.1 calculations, ASHRAE level 1 audit, and water saving calculations.

LEED Gold
Alternative Transportation 15/15
Sustainable Sites: 3 / 10
Water Efficiency: 9 / 12
Energy and Atmosphere: 17 / 38
Materials and Resources: 4 / 8
Indoor Environmental Quality: 9 / 17
Innovation and Design: 3 / 6