Total Energy Saved
Building A: 670 MMBTU
Building B: 255 MMBTU
Building C: 132 MMBTU
Building D: 120 MMBTU
Building E: 1,433 MMBTU
Building F: 207 MMBTU
Date of Completion
February 2013
Building C
Project Overview
BTU Engineers provided energy modeling and LEED commissioning for 6 buildings in Culver City, CA. The total area is approximately 41,253 square feet of retail and restaurant, and 38,120 square feet of office. There are two above ground parking structures, one existing and the other new, which accommodates a total of 291 parking spaces.
The Platform at Culver Station is a retail, office, and parking project that includes adaptive reuse of some existing buildings in conjunction with new construction to create a community oriented niche shopping environment with some office above. The broad theems that drive the design are transportation, pedestrian flow, and sustainability.